Industrial Process

P&G Project Double Down Building Addition

St. Louis, MO

Doubling manufacturing capacity through integrated delivery and Lean construction

Market

Industrial Process

Key Services

Construction

Preconstruction

Self-Perform

Strategic Partnerships

Delivery Method
Integrated Project Delivery (IPD)
Capacity
21,700 SF

The challenge

Procter & Gamble partnered with Alberici to expand its St. Louis home care products manufacturing facility with a 17,500 SF building addition, a new 4,200 SF process building and a three-bay loading dock expansion. The project doubled the plant’s production capacity while creating space for a future packaging line and accommodating increased shipments

Delivered through an Integrated Project Delivery (IPD) model, Alberici collaborated with Procter & Gamble and the design team under an Integrated Form of Agreement (IFOA), aligning all participants through shared risks, rewards and project goals. Lean construction principles guided collaborative design sessions and target value design workshops to maximize value while maintaining budget and schedule

Key Facts

2X manufacturing capacity through strategic facility expansion


Three-bay dock expansion accommodates increased outbound shipments


Over $400,000 in savings achieved through lean construction and collaboration


Challenge met

By applying lean planning from design through construction, Alberici helped reduce project costs by more than $400,000, approximately 4% of the project’s estimated value. Collaborative decision-making, target value design and continuous process improvements enhanced efficiency, maximized owner value and delivered the expansion in alignment with Procter & Gamble’s conditions of satisfaction.