Skip to main content
Energy & Renewables

Meldahl Hydroelectric Project

Foster, Kentucky

Successfully completing the largest hydroelectric plant on the Ohio River

Market

Energy & Renewables

Key Services

Construction

Self-Perform

Strategic Partnerships

Virtual Design & Construction

Self Perform %
79
Capacity
105 MW
Work Hours
2,450,000

The challenge

Alberici led a joint venture team to construct the Meldahl Hydroelectric Plant. This project was part of a larger program to deploy the largest clean, renewable run-of-the river hydroelectric plant in the country. The powerhouse is designed to be overtopped during flood events by as much as 25 feet of water.  During a period in the spring of 2015, construction continued inside the powerhouse while the entire powerhouse was submerged under 10 feet of water. Challenges included installation of a 175-ton powerhouse crane, which we later used to install the plant’s three bulb-type, 35 MW turbine generators. Our project team installed more than 5 million pounds of electrical and mechanical equipment, including massive water control structures with tolerances of a half-millimeter.

After construction of the structure was complete and the site was re-watered, Alberici coordinated a team of divers to perform inspections and perform hydraulic dredging of the intake structure at depths of up to 105 feet.

Key Facts

105 megawatts


Three horizontal bulb turbines


900 concrete placements

Challenge met

Alberici’s solution encompassed cutting-edge strategies and meticulous planning. A comprehensive 3D model and virtual schedule were developed to visualize construction sequencing within the powerhouse, enhancing accuracy and project insight. To manage groundwater seepage, an elaborate pump system was employed, discharging up to 5,500 gallons per minute around the clock to prevent flooding.

Emphasizing self-performance, Alberici’s skilled team undertook 79 percent of all work, including batch plant setup, concrete placement, steel erection, and equipment assembly. With innovative lift drawings, more than 900 individual concrete placements were precisely executed. An onsite batch plant facilitated seamless concrete production, ensuring quality and efficiency. Upon completion, the batch plant was transformed into a community recreation area.

Through strategic foresight, technical expertise, and collaborative coordination, Alberici navigated complexities to successfully deliver the hydroelectric plant. The project stands as a testament to Alberici’s commitment to innovation, precision, and excellence in challenging construction environments.

Recent Projects

SaskPower Queen Elizabeth Combined Cycle Repowering

Empire Energy Air Quality Control Project

Shell Pennsylvania Petrochemicals Complex