Little Blue Valley Sewer District Atherton Wastewater Treatment Plant
Previous 1 of 2 Next

Client: Little Blue Valley Sewer District
Location: Independence, Missouri, United States
Project Type: Wastewater Treatment Facility
Contract Amount: $73,000,000 USD
Delivery Method: General Contracting
Project Size: N/A
Start Date: June 2003
Completion Date: June 2006
Architect/Engineer: Archer/CH2M Hill

( Large Map | Satellite Map )

Participating Alberici Enterprises

Little Blue Valley Sewer District Atherton Wastewater Treatment Plant

Alberici Constructors was selected to provide $73 million of improvements and upgrades to the Atherton Wastewater Treatment Plant.  The improvements and upgrades will allow the plant to increase its capacity from 40mgd to 52mgd and eliminate a major source of odor for the surrounding communities.

 

A major challenge on the project is constructing while the plant remains in full operation.  The transition from the existing water/sewage service lines to the new system must be done without shutting down the plant's ability to process sewage from the communities it serves.

 

To meet demanding schedule requirements Alberici constructed many of the major concrete structures through the winter months of 2003-04.  This required careful selection of form systems and concrete placement methods to be sure they were most appropriate for cold weather.